Steel- and Metal Construction Works Nuclear Power Plant Olkiluoto, Finland EPC

Project
In the course of the main contract, which was already completed in May 2007 for the “carcass construction of the new buildings”, Heitkamp was also contracted for the steel and metal works for the following service areas:
Ladders, ladder walkthroughs, gratings, railings, special steel platforms with in part highest requirements for fire safety,  airtight metal sheet covers in safety zones of the reactor building, various other metal sheet guards. Furthermore, detail solutions that become necessary in the implementation planning and/or implementation are manufactured directly in own construction site production.

Client
Areva NP GmbH,
Offenbach

Construction time
2010 – 2013

Planner
Heitkamp Ingenieur- und
Kraftwerksbau GmbH